A Review Paper on Critical Chain Project Management

Method in Construction Project

Divyesh Sharma1

, Sonam Yadav2

1Research Scholar, IES IPS Academy Indore-452001, MP, India

Email: divyesh67sharma@gmail.com

2Asst. Professor, IES IPS Academy Indore-452001, MP, India

Abstract:

Present research is oriented and focuses to

analyze construction project management

technique and methodology for under

construction buildings taken as a live practical

case for research as a problem location, i.e. the

critical chain project management (CCPM).

The research is identified to show offers and

effect of CCPM technique to improve project

performance and help decision for manager for

improvement in existing method of construction

and its planning. It is required to plan and

design CPM and CCPM together, as CPM

never offers execution methodology and must be

subordinate to CCPM for execution of on time

and under controlled cost project completion.

The trends and original time and operational

sequence records are collected for considered

building construction cases to identify and trace

overall activities on time scale. MSP (Microsoft

Project) software is used to record data and to

find critical path for building construction. The

aim is to reduce time and hence cost of project

utilizing CCPM and MSP together. Suggestions

are scientifically implemented for activity and

sequence of activities to improve project time.

Improved suggested project schedule is

compared with existing schedule to show results

in comparative format with graphs and charts

to prove effectiveness of CCPM and MSP

utility.

Key words: CCPM, Microsoft Project, Project

Management, Scheduling.

1. INTRODUCTION

Project is an effort taken to construct any

product in this world. Project is having start and

end dates. It depends on resources available and

produced to use. Project is required to complete

in limited duration of time and schedule is the

activity performed by project manager to

accomplish and achieve project in time with

minimum cost.

It is observed from past trends, records and

experiences that about 50% of the time and cost

is over estimated which was never been

considered for project. This unexpected hike in

cost tends to fail project estimation and

duration.

CCPM overcomes many construction project

problems and is major evaluation in the field of

construction project management. It helps to

schedule and complete project in

time as well it provides buffer time duration to

protect problems and duration increase during

project execution. In addition to provide a

quicker way of completing project. Moreover,

CCPM employs buffers to act as safeguards

against various problems that may arise during

the execution of the projects.

MS Project is a software tool used in project

management, it is developed, published and

marketed by Microsoft. It is designed to be used

in management of projects to develop plan, to

assign resources for various tasks, to track the

preplanned progress of construction process, to

manage the available budget and to investigate,

study and analyze work load in the

organization.

The software is having spread sheet

environment in which the project manager can

feed start and end task row by row for each

activity of the project. Project manager can also

assign the resources such and labor,

Page 2 of 4

Journal for Studies in Management and Planning

Available at http://edupediapublications.org/journals/index.php/JSMaP/

ISSN: 2395-0463

Volume 03 Issue 02

February 2017

Available online: http://edupediapublications.org/journals/index.php/JSMaP/ P a g e | 15

equipment’s and material for each of the

activity. The complete tasks can also be

assigned with subtasks. The process is then can

be seen with Gantt chart which is appeared at

half right side of the screen. Gantt chart

represents the activities alternative and parallel

too. Project manager can also view critical path

for the project without performing any

computational or mathematical approach and

investing time.

2. Review

Muller (2001) Paper presented, CCPM using

Buffers and Risk. This paper shows how

statistical process control with the use of

function points and standard process can

improve the ability to plan and control projects.

Using examples based on real-life experience, it

provides a simple method for controlling

variation and risk.

Jan and Shu-Hui (2006), Project scheduling

and its control for construction application is

critical and difficult due to limited resources. It

always cost high with uncontrolled schedule.

Theory of constraints and CCPM i.e. critical

chain management is proposed to control

activities for their completion in time duration.

Buffer is availed to project manager for

effective schedule and control. The study in this

paper explained the applications of critical

chain and buffers for construction planning,

control and management in shorter duration of

time.

There are many hidden constraints which

cannot be identified, solved or handled by

traditional CPM/PERT techniques. Critical

chain with buffer effectively removes those

hidden constraints. This study assigns safety

time for each activity in construction and hence

it overcome extended duration problem

efficiently.

Stratton (2008), Critical chain was introduced

in 1997 first, then software and their

implementation in construction practices starts

to develop for construction project

management. Strategy and tactic tree is

proposed and applied to review CCPM

theoretically and practically with new improved

guidelines. The paper includes the new

findings and approaches with respect to current

practices in construction industry. Paper

concludes success of CCPM in construction

industry, with strategy and tactic tree for the

growth and betterment of CCPM for control and

continuous improvement of construction

activities and industries.

Robinson (2009), The researcher in this paper

investigates and presents the success of critical

chain in construction project. Research

elaborates applications of critical chain

including construction projects. Many reasons

for failure of projects are listed and critical

chain is suggested as a solution project

management approach for project. It is

concluded that buffers provided using critical

chain approach results in lesser project duration

and is more cost and time effective than any

other project scheduling methods.

Kulkarni et al. (2009), Project management is

noticed as a critical and difficult task and

Critical chain is highly required due to the need

of timely completion of the project and to

improve service. Human behavior aspect is also

discussed and addressed for any project success.

It was concluded that CCPM provides better

even excellent solutions and can be used

parallel to or with CPM. MS Project was used

in this paper to schedule construction project

and time reduced by 20% to 30% can be

converted into saving of cost and hence profit.

Stelth (2009), Construction projects are

analyzed and scheduled with critical path

method or techniques to find and determine

longest path for construction project.

Organizations are now a days motivated to

assign or recruit a virtual project management

team. The virtual project management team

works with advanced techniques and even

procurement of material is promoted from all

corners of world. The advanced techniques too

create their own challenges and problem which

are addressed in this research paper. New