A Review Paper on Critical Chain Project Management
Method in Construction Project
Divyesh Sharma1
, Sonam Yadav2
1Research Scholar, IES IPS Academy Indore-452001, MP, India
Email: divyesh67sharma@gmail.com
2Asst. Professor, IES IPS Academy Indore-452001, MP, India
Abstract:
Present research is oriented and focuses to
analyze construction project management
technique and methodology for under
construction buildings taken as a live practical
case for research as a problem location, i.e. the
critical chain project management (CCPM).
The research is identified to show offers and
effect of CCPM technique to improve project
performance and help decision for manager for
improvement in existing method of construction
and its planning. It is required to plan and
design CPM and CCPM together, as CPM
never offers execution methodology and must be
subordinate to CCPM for execution of on time
and under controlled cost project completion.
The trends and original time and operational
sequence records are collected for considered
building construction cases to identify and trace
overall activities on time scale. MSP (Microsoft
Project) software is used to record data and to
find critical path for building construction. The
aim is to reduce time and hence cost of project
utilizing CCPM and MSP together. Suggestions
are scientifically implemented for activity and
sequence of activities to improve project time.
Improved suggested project schedule is
compared with existing schedule to show results
in comparative format with graphs and charts
to prove effectiveness of CCPM and MSP
utility.
Key words: CCPM, Microsoft Project, Project
Management, Scheduling.
1. INTRODUCTION
Project is an effort taken to construct any
product in this world. Project is having start and
end dates. It depends on resources available and
produced to use. Project is required to complete
in limited duration of time and schedule is the
activity performed by project manager to
accomplish and achieve project in time with
minimum cost.
It is observed from past trends, records and
experiences that about 50% of the time and cost
is over estimated which was never been
considered for project. This unexpected hike in
cost tends to fail project estimation and
duration.
CCPM overcomes many construction project
problems and is major evaluation in the field of
construction project management. It helps to
schedule and complete project in
time as well it provides buffer time duration to
protect problems and duration increase during
project execution. In addition to provide a
quicker way of completing project. Moreover,
CCPM employs buffers to act as safeguards
against various problems that may arise during
the execution of the projects.
MS Project is a software tool used in project
management, it is developed, published and
marketed by Microsoft. It is designed to be used
in management of projects to develop plan, to
assign resources for various tasks, to track the
preplanned progress of construction process, to
manage the available budget and to investigate,
study and analyze work load in the
organization.
The software is having spread sheet
environment in which the project manager can
feed start and end task row by row for each
activity of the project. Project manager can also
assign the resources such and labor,
Page 2 of 4
Journal for Studies in Management and Planning
Available at http://edupediapublications.org/journals/index.php/JSMaP/
ISSN: 2395-0463
Volume 03 Issue 02
February 2017
Available online: http://edupediapublications.org/journals/index.php/JSMaP/ P a g e | 15
equipment’s and material for each of the
activity. The complete tasks can also be
assigned with subtasks. The process is then can
be seen with Gantt chart which is appeared at
half right side of the screen. Gantt chart
represents the activities alternative and parallel
too. Project manager can also view critical path
for the project without performing any
computational or mathematical approach and
investing time.
2. Review
Muller (2001) Paper presented, CCPM using
Buffers and Risk. This paper shows how
statistical process control with the use of
function points and standard process can
improve the ability to plan and control projects.
Using examples based on real-life experience, it
provides a simple method for controlling
variation and risk.
Jan and Shu-Hui (2006), Project scheduling
and its control for construction application is
critical and difficult due to limited resources. It
always cost high with uncontrolled schedule.
Theory of constraints and CCPM i.e. critical
chain management is proposed to control
activities for their completion in time duration.
Buffer is availed to project manager for
effective schedule and control. The study in this
paper explained the applications of critical
chain and buffers for construction planning,
control and management in shorter duration of
time.
There are many hidden constraints which
cannot be identified, solved or handled by
traditional CPM/PERT techniques. Critical
chain with buffer effectively removes those
hidden constraints. This study assigns safety
time for each activity in construction and hence
it overcome extended duration problem
efficiently.
Stratton (2008), Critical chain was introduced
in 1997 first, then software and their
implementation in construction practices starts
to develop for construction project
management. Strategy and tactic tree is
proposed and applied to review CCPM
theoretically and practically with new improved
guidelines. The paper includes the new
findings and approaches with respect to current
practices in construction industry. Paper
concludes success of CCPM in construction
industry, with strategy and tactic tree for the
growth and betterment of CCPM for control and
continuous improvement of construction
activities and industries.
Robinson (2009), The researcher in this paper
investigates and presents the success of critical
chain in construction project. Research
elaborates applications of critical chain
including construction projects. Many reasons
for failure of projects are listed and critical
chain is suggested as a solution project
management approach for project. It is
concluded that buffers provided using critical
chain approach results in lesser project duration
and is more cost and time effective than any
other project scheduling methods.
Kulkarni et al. (2009), Project management is
noticed as a critical and difficult task and
Critical chain is highly required due to the need
of timely completion of the project and to
improve service. Human behavior aspect is also
discussed and addressed for any project success.
It was concluded that CCPM provides better
even excellent solutions and can be used
parallel to or with CPM. MS Project was used
in this paper to schedule construction project
and time reduced by 20% to 30% can be
converted into saving of cost and hence profit.
Stelth (2009), Construction projects are
analyzed and scheduled with critical path
method or techniques to find and determine
longest path for construction project.
Organizations are now a days motivated to
assign or recruit a virtual project management
team. The virtual project management team
works with advanced techniques and even
procurement of material is promoted from all
corners of world. The advanced techniques too
create their own challenges and problem which
are addressed in this research paper. New